New City Upgrades Weekly Series May 4, 2010
Phase 2A Asphalt Paving Systems
Ninth and 14th avenues
Restoration of all grass and topsoils - completed
Final Paving - completed
Stiping of Roads - Complete
Punch list revised - May 1, 2010
Punch list completion to follow
Additional paving to remove depression from Surf - complete
Phase 2B Perna Finnigan Construction
New York Avenue
Blocks 22 - 26 milling and grading - completed
Blocks 22-26 base pavement - completed
Blocks 10- 12 Installation of concrete gutter and curb - completed
Blocks 10-12 Installation of base pavement to follow South Jersey Gas
Installation
Blocks 12-15th Installation of new gas main - complete
Blocks 13-15th storm installation - complete
Blocks 13-15th sewer and water lateral installation - complete 5/7/2010
Blocks 13-15th Installation of concrete - complete 5/16/2010
Blocks 13-15th Installation of base pavement to follow
Blocks 15-17th installation of new sewer main - completed
Blocks 15-17th Installation of storm sewer -complete 4/30/2010
Blocks 15-17th Installation of sewer and water laterals - 5/7/2010
Blocks 15-17th Installation of concrete - 5/21/2010
Blocks 15-17th Installation of new water main - complete 5/7/2010
Blocks 15-17th Installation of base pavement to follow
Blocks 17-19th Installation of sewer main - complete 4/30/2010
Blocks 22-19th Installation of sanitary sewer - complete 5/7/2010
Blocks 22-19th Installation of storm sewer - complete 5/16/2010
12 Street
100 Block installation of services - complete
100 Block installation of concrete - complete
200 Block installation of new sewer main - complete
200 Block installation of sewer and water laterals - complete
100 and 200 Block base pavement - completed following week
|